Projects

Road or bridge · Roads and bridges

Travaux de modernisation de 22,21 km de la voirie urbaine dans la Ville de Kalemie

Communes de Kalemie, de la Lukuga et du Lac, Ville de Kalemie, Province du Tanganyika
Start: 30/05/2026 · End: 30/11/2028

Ongoing

Assess this project Report a problem Map

Road or bridge
  • physical progress
  • 41,8 M $USplanned cost
  • —of the budget line paid
  • 0problems found
  • 0monitoring visits

About the project

Modernisation de 22,21 km de voirie urbaine à Kalemie : chaussée rigide, systèmes de drainage, bordures, éclairage public, signalisation routière et ouvrages d’assainissement. Les travaux touchent les trois communes : Kalemie (3,8 km), Lukuga (10,87 km) et Lac (7,35 km). Le ministre des Infrastructures et Travaux publics, John Banza Lunda, a lancé les travaux le samedi 30 mai 2026. Durée prévue : 30 mois. Coût estimé : 41,8 millions de dollars américains, financés par le Trésor public. Supervision : Office des voiries et drainage (OVD). Contrôle : Bureau technique de contrôle (BTC).

How is the project going?

0 problems · 0 points in order, from the latest visits

Physical progress—
Time elapsed18 %

No monitoring visit published yet for this project.

Assess this project

One form for this road or bridge, in three parts: the project visit, the building site and the questions specific to this type of infrastructure. Geotagged photos are required; a proof can be added under each answer.

  1. Monitoring an investment project 8 questions

    Site visit: does the project exist, is work progressing, is the quality acceptable and is it being used? Geotagged photos are required.

  2. Building-site monitoring 14 questions

    On every building site: contract and bill of quantities shown, site board, materials, safety, payments and signs of corruption.

  3. Road and bridge 8 questions

    Length and width, road surface, drainage, culverts and bridges, road safety, compensation of residents, maintenance.

Log in to assess30 questions in all

Do you live here and want to keep an eye on this budget? Become a community monitor →

Survey of the direct beneficiaries

Interviews of the people the project is meant to serve: need, consultation, usefulness, who to contact, money asked for, quality, satisfaction. One form per person, without name or contact.

Not enough answers yet (0 of 5 needed before publication).

Log in to assess

Latest visits

No monitoring visit published yet for this project.