Réhabilitation des lignes électriques SNEL alimentant Uvira

Lignes d’alimentation de la ville, Ville d’Uvira
Start: 01/01/2025 · End: 31/12/2025

Completed

Assess this project Report a problem

Electricity and energy
  • physical progress
  • —planned cost
  • —of the budget line paid
  • 0problems found
  • 0monitoring visits

About the project

D’après le bilan 2025 du CICR en RDC, deux grandes lignes électriques de la SNEL alimentant Goma et Uvira ont été réhabilitées par la SNEL avec le CICR comme intermédiaire neutre. Le CICR a aussi fourni du carburant à la REGIDESO et à des hôpitaux d’Uvira pour maintenir la production d’eau et d’électricité, ainsi que des produits de traitement de l’eau à la REGIDESO d’Uvira.

Reported by Kalunga Josephine Candy

How is the project going?

0 problems · 0 points in order, from the latest visits

Physical progress100 %
Time elapsed100 %

No monitoring visit published yet for this project.

Assess this project

One form for this electricity and energy, in three parts: the project visit, the building site and the questions specific to this type of infrastructure. Geotagged photos are required; a proof can be added under each answer.

  1. Suivi d'un projet d'investissement 8 questions

    Site visit: does the project exist, is work progressing, is the quality acceptable and is it being used? Geotagged photos are required.

  2. Suivi de chantier 14 questions

    On every building site: contract and bill of quantities shown, site board, materials, safety, payments and signs of corruption.

  3. Électricité et énergie 7 questions

    Poles, street lights or solar panels installed and working, safe wiring, connections, tariffs displayed, maintenance.

Log in to assess29 questions in all

Do you live here and want to keep an eye on this budget? Become a community monitor →

Survey of the direct beneficiaries

Interviews of the people the project is meant to serve: need, consultation, usefulness, who to contact, money asked for, quality, satisfaction. One form per person, without name or contact.

Not enough answers yet (0 of 5 needed before publication).

Log in to assess

Latest visits

No monitoring visit published yet for this project.