School · Éducation
Réhabilitation de l’école primaire du centre (démo)
Ville de Bukavu · Province du Sud-Kivu · Ville de Bukavu
Budget 2026
Ongoing Behind schedule Demonstration data
- physical progress
- 1,1 bn CDFplanned cost
- —of the budget line paid
- 4problems found
- 1monitoring visits
How is the project going?
4 problems · 3 points in order, from the latest visits
- En partie
Le projet existe-t-il physiquement à l'endroit indiqué ?
- En partie
L'avancement physique est-il conforme au calendrier ?
- En partie
L'ouvrage achevé est-il fonctionnel et utilisé par la population ?
- En partie
La main-d'œuvre locale a-t-elle été employée ?
Points in order (3)
- Un panneau de chantier indique-t-il le coût, l'entreprise, la source de financement et les délais ?
- La qualité des travaux et des matériaux paraît-elle conforme ? (observations, photos)
- Des plaintes de riverains ou d'usagers existent-elles ?
Assess this project
One form for this school, in three parts: the project visit, the building site and the questions specific to this type of infrastructure. Geotagged photos are required; a proof can be added under each answer.
Suivi d'un projet d'investissement 8 questions
Site visit: does the project exist, is work progressing, is the quality acceptable and is it being used? Geotagged photos are required.
Suivi de chantier 14 questions
On every building site: contract and bill of quantities shown, site board, materials, safety, payments and signs of corruption.
École 8 questions
Classrooms, separate latrines for girls and boys, furniture, access for pupils with disabilities, parents’ committee.
Log in to assess30 questions in all
Do you live here and want to keep an eye on this budget? Become a community monitor →
Survey of the direct beneficiaries
Interviews of the people the project is meant to serve: need, consultation, usefulness, who to contact, money asked for, quality, satisfaction. One form per person, without name or contact.
Not enough answers yet (0 of 5 needed before publication).